New shops

Licences since July 2025. The date is when the city approved it, not the opening day.

Show 17 moreShow fewer

Named on a permit

A permit application that names a shop. It is not a licence and not an opening day.

Permit application

Tim Horton

101 College St · University-Rosedale

Applied 1 Sep 2026

Inspection

Interior alterations to an existing suite - including minor architectural, HVAC, plumbing, & electrical work - "Tim Horton's"

Being built

The city has allowed these. Work may not have started.

Student Residence

333 College St

333 College St · University-Rosedale

Approved 9 Nov 2026

Conditional Permit - Part Permit - Proposal to construct 20 storey, 553 Unit (706 Beds), Student Residence building with retail on ground floor.

Multiple Unit Building

646 College St

646 College St · University-Rosedale

Approved 4 Nov 2026

Revision No. 3: Propsoed Office on third floor and second floor as storage serving office above.Revision 02 - Proposed interior alterations to 3rd-floor change of use from residential to commerical…

Multiple Unit Building

938 College St

938 College St · Davenport

Approved 25 Aug 2026

Proposal to replace existing window with new entrance door, for existing ground floor restaurant. Alterations to basement exit stair with new separation.

Show 14 moreShow fewer
Multiple Unit Building

80 College St

80 College St · University-Rosedale

Approved 14 Jul 2026

New non-life-safety generator on roof including new natural gas piping, electrical, structural for generator.

Multiple Unit Building

14 College St

14 College St · Toronto Centre

Approved 24 Jun 2026

Proposal to remove existing entrance steps and reconstruct the entrance.

Multiple Unit Building

861 College St

861 College St · Davenport

Approved 18 Jun 2026

REMOVE AND RECONSTRUCT EXTERIOR FIRE ESCAPE STAIRCASE

Multiple Unit Building

863 College St

863 College St · Davenport

Approved 18 Jun 2026

REMOVE AND RECONSTRUCT EXTERIOR FIRE ESCAPE STAIRCASE

1 homes

281 College St

281 College St · University-Rosedale

Approved 21 Apr 2026

1 new home

The permit lists 1 homes.

Revision 01: Change of use from office to dwelling unit on main floor. Proposal for interior alterations to convert the main floor into 2 commercial units with offices proposed at teh back unit.

Multiple Unit Building

853 College St

853 College St · Davenport

Approved 10 Feb 2026

Proposed refacing of existing front facade

Multiple Unit Building

489 College St

489 College St · University-Rosedale

Approved 4 Dec 2025

REV: Remove existing corridor doors where indicated in plan and replace exit doors to a temperature rise doors on 1-5 floors

Multiple Unit Building

199 College St

199 College St · University-Rosedale

Approved 10 Oct 2025

Proposal for retention of designated heritage facades during demolition as per Heritage Preservation Plan.

Multiple Unit Building

1156 College St

1156 College St · Davenport

Approved 10 Jun 2025

Admin partywall permit in conjunction with 25 144380 BLD, 1158 College St.

Multiple Unit Building

1158 College St

1158 College St · Davenport

Approved 10 Jun 2025

Proposal for interior alteration in basement and underpinning.

Multiple Unit Building

975 College St

975 College St · Davenport

Approved 6 Mar 2025

Rev 02 - To maintain existing building envelope, including roofs, exterior walls, deck, and add enclosed stairs at rear.Revision 01 - to maintain existing building envelope, including roofs, exterior walls and deck and…

Multiple Unit Building

828 College St

828 College St · University-Rosedale

Approved 24 Feb 2025

Rev - Demolition and construction of new Interior staircase at 830 College Basement (Stair B) and new Interior Partitions, revised HVAC System and Plumbing to suit entire Base Building improvements.Proposed partial…

Multiple Unit Building

865 College St

865 College St · Davenport

Approved 29 Jan 2025

INTERIOR ALTERNATIONS TO SECOND AND THIRD FLOOR; COMBINE TWO EXISTING DWELLING UNITS IN TO ONE FOR A TOTAL OF TWO DWELLING UNITS TO REMAIN.. EXTERIOR STAIR RENOVATION

Coming down

The city has allowed these buildings to come down. They may still be standing.

Demolition

1280 College St

1280 College St · Davenport

Approved 26 May 2026

The existing car wash will be demolished to facilitate the development of a new 8-storey residential building.

Demolition

333 College St

333 College St · University-Rosedale

Approved 15 Dec 2025

Proposed to demolish one-storey modular commercial unit in preparation for a new 20-storey building.

Demolition

199 College St

199 College St · University-Rosedale

Approved 16 Oct 2025

Partial demolition of a mixed use three storey building. Retention of designated heritage facades as per Heritage Preservation Plan

Show 3 moreShow fewer
Demolition

193 College St

193 College St · University-Rosedale

Approved 16 Oct 2025

Partial demolition of a mixed use three storey building. Retention of designated heritage facades as per Heritage Preservation Plan

Demolition

195 College St

195 College St · University-Rosedale

Approved 16 Oct 2025

Partial demolition of a mixed use three storey building. Retention of designated heritage facades as per Heritage Preservation Plan

Demolition

191 College St

191 College St · University-Rosedale

Approved 16 Oct 2025

Partial demolition of a mixed use three storey building. Retention of designated heritage facades as per Heritage Preservation Plan

Loud nights

Hours the city has already allowed.

Continuous Concrete Pour

333 College Student Residences

333 College St · University-Rosedale

Allowed 15 Oct 2026 – 12 Apr 2027

Hours from 7:00 a.m.

Hsre Parallax I Lp

Events

On the city's calendar. Check before you go.

Arts/ExhibitsArtisan

Woodlawn Pottery Show & Sale

967 College St · Davenport

On 21 Nov 2026 – 22 Nov 2026

Free

20+ artists. 100+ designs. This beloved annual event celebrates the creativity and craftsmanship of Woodlawn's vibrant

Event pageAdd to calendar

Plans you can answer

Someone has asked the city for a change. Nothing here is a decision.

Site plan

150 College St

150 College St · University-Rosedale

Asked 18 Mar 2026

Under Review

The proposed development has a height of 9-storeys above-grade (41.4 metres to the top of the main building) with additional rooftop mechanical penthouses and projecting elements (55.4 metres to the highest point of these elements). The proposed development consists of a gross floor area of 25,387 square metres.

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Esha Biddanda Pavan · [email protected].

Site plan

976 College St

976 College St · Davenport

Asked 10 Jul 2025

NOAC Issued

Site Plan Approval for a 6-storey mass timber residential building for 19 affordable dwelling units.

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Doris Ho · [email protected].

Site plan

191 College St

191 College St · University-Rosedale

Asked 28 Aug 2022

Under Review

Related App 22 150580 STE 11 OZSite Plan application for proposal for a 31-storey mixed-use building containing 492 purpose-built rental units. The proposed non-residential gross floor area is 1,379 square metres, and the proposed residential gross floor area is 19,924 square metres.

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Konain Edhi · [email protected].

Show 2 moreShow fewer
Site plan

833 College St

833 College St · Davenport

Asked 26 May 2022

Under Review

INACTIVE Proposed development consists of a six (6) storey mixed-use building including 58.4 square metres of commercial space at grade and 5 residential dwelling units above totaling 982.48 square metres. Proposed pedestrian access to the commercial unit is proposed from College Street and proposed pedestrian and…

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Doris Ho · [email protected].

Site plan

355 College St

355 College St · University-Rosedale

Asked 29 Jan 2018

NOAC Issued

Proposal for site plan approval related to a five storey addition to existing hostel with portion of ground floor to be used as retail

How to respond