Opening this block

Home · Toronto-St. Paul's · Hillsdale Ave E

What's new around 131 Hillsdale Ave E

131 Hillsdale Ave E · Toronto-St. Paul's. Within 1 km.

New shops

Licences since July 2025. The date is when the city approved it, not the opening day.

Show 21 moreShow fewer

Being built

The city has allowed these. Work may not have started. The permits in this area list 2032 homes.

New house

131 Hillsdale Ave E

0 m away · 131 Hillsdale Ave E · Toronto-St. Paul's

Approved 23 Jul 2026

Nikan Sharif-zadeh

REV 02: REVISION TO BASEMENT LAYOUT. MINOR CHANGES TO WALKOUT, MAIN & 2ND FLOOR INDICATED WITH REVISION CLOUDS.Proposal to construct a new 2 storey single family dwelling and demolish the existing 2 storey single family…

New house

11 Oswald Cres

197 m away · 11 Oswald Cres · Toronto-St. Paul's

Approved 11 Sep 2026

2 new homes · 16230288 Canada Inc

The permit lists 2 homes.

TO CONSTRUCT A NEW TWO STOREY DUPLEX

New house

12 Cuthbert Cres

285 m away · 12 Cuthbert Cres · Toronto-St. Paul's

Approved 20 May 2025

2 new homes

The permit lists 2 homes.

Proposal to construct a new 2 unit semi detached house - related to 24 193610 BLD 00 NH

Show 21 moreShow fewer
Apartment

2161 Yonge St

323 m away · 2161 Yonge St · Toronto-St. Paul's

Approved 22 Jul 2025

31 new homes

The permit lists 31 homes.

REVISION - to add 3 additional floorsProposal to construct a new 35 storey mixed use building with 304 dwelling units, office and retail space and 5 levels of underground parking. See also 17 1862503 SA

Apartment

18 Brownlow Ave

335 m away · 18 Brownlow Ave · Toronto-St. Paul's

Approved 23 Jun 2026

194 new homes

The permit lists 194 homes.

Application to construct a 27 storey purpose built residential building with 194 dwelling units and 3 levels of below grade parking garage (Below grade connections to existing parking garage to the property to the west-…

Multiple Unit Building

2150 Yonge St

345 m away · 2150 Yonge St · Toronto-St. Paul's

Approved 3 Sep 2026

Revision 1: Revision to the building permit illustrating the pre-fire and post-repair ceiling height at the base of the basement staircaseProposed fire damage repairs. Scope includes removal and replacement of gypsum,…

Multiple Unit Building

2191 Yonge St

347 m away · 2191 Yonge St · Toronto-St. Paul's

Approved 1 May 2026

Proposal for interior alterations to first floor and third floor amenities area

Multiple Unit Building

688 Mount Pleasant Rd

399 m away · 688 Mount Pleasant Rd · Toronto-St. Paul's

Approved 6 Nov 2026

Revision 01: New scope includes full interior renovation of the basement and ground floors including architectural, structural, hvac, electrical and plumbing and drainage for personal Service Shop (Beauty…

Multiple Unit Building

598 Mount Pleasant Rd

418 m away · 598 Mount Pleasant Rd · Toronto-St. Paul's

Approved 24 Jul 2026

Rear addition. Commercial building. Ground floor medical office; second storey office

Multiple Unit Building

2200 Yonge St

447 m away · 2200 Yonge St · Toronto-St. Paul's

Approved 27 May 2026

Proposal for localized asphalt, waterproofing, expansion joint, and concrete repairs at Upper Deck of parking garage

Multiple Unit Building

1995 Yonge St

448 m away · 1995 Yonge St · Toronto-St. Paul's

Approved 20 Mar 2026

Rev 01 - Change of Use from A2 to C occupancy on 2nd floor, and interior alterations of an existing suite including architectural, HVAC, plumbing, and electrical work.Proposal for interior alterations of existing suite.

1 homes

176 Eglinton Ave E

456 m away · 176 Eglinton Ave E · Toronto-St. Paul's

Approved 9 Oct 2026

1 new home

The permit lists 1 homes.

Reconstruction of the existing deck and exterior stairs, including the construction of new reinforced concrete masonry unit (CMU) walls to support the new deck.

Multiple Unit Building

8 Eglinton Ave E

473 m away · 8 Eglinton Ave E · Toronto-St. Paul's

Approved 19 Oct 2026

Proposal for interior alterations to vacant unit RU05 into a Group E (Acai Shop).

Laneway suite

34 Hadley Rd

519 m away · 34 Hadley Rd · Don Valley West

Approved 17 Dec 2025

1 new home

The permit lists 1 homes.

Proposal to construct a new detached laneway suite.

Multiple Unit Building

2300 Yonge St

555 m away · 2300 Yonge St · Eglinton-Lawrence

Approved 6 Aug 2026

proposal for localized concrete repairs and waterproofing renewal at the parking garage helical ramp

Multiple Unit Building

1951 Yonge St

574 m away · 1951 Yonge St · Toronto-St. Paul's

Approved 21 May 2026

Shoring and excavation for remediation purposes

New house

29 Taunton Rd

578 m away · 29 Taunton Rd · Don Valley West

Approved 26 Sep 2025

1 new home · Michelle Basu Roy

The permit lists 1 homes.

Fire damage dwelling to be rebuilt from ground to third floor including front porch, a new walk out to be constructed, Existing basement/foundation walls and concrete slab-on-grade. Front porch concrete steps to remain

Apartment

170 Roehampton Ave

588 m away · 170 Roehampton Ave · Toronto-St. Paul's

Approved 28 Jul 2026

599 new homes

The permit lists 599 homes.

Construction of new 50-storey Purpose-Built Rental (PBR) Residential Building, with 599 dwelling units, 8-storey podium and 2-level underground parking garage.

Multiple Unit Building

1920 Yonge St

647 m away · 1920 Yonge St · Toronto-St. Paul's

Approved 20 Apr 2026

Proposal for interior alterations to existing office space - UNIT 500

New house

88 Colin Ave

650 m away · 88 Colin Ave · Toronto-St. Paul's

Approved 1 Jun 2026

1 new home · Georgina Myers

The permit lists 1 homes.

To construct a new single family dwelling

New house

52 Imperial St

650 m away · 52 Imperial St · Toronto-St. Paul's

Approved 21 Jan 2025

1 new home · Haddington Developments Inc

The permit lists 1 homes.

REV 01 - Revision for 1 - washroom added in lower basement level.2 - increased size of mech. space in attic.3 - ground floor FFE was slightly raised. All other floor heights are unchanged.4 - grading plan has been…

Mixed Use/res W Non Res

65 Broadway Ave

670 m away · 65 Broadway Ave · Toronto-St. Paul's

Approved 23 Jan 2025

Revision 01- as per cover letterProposal to construct 2, 39 storey residential towers with a daycare at grade and 4 levels of below grade parking.

Coming down

The city has allowed these buildings to come down. They may still be standing.

Demolition

68 Soudan Ave

184 m away · 68 Soudan Ave · Toronto-St. Paul's

Approved 22 Jan 2025

Demolish the existing two storey semi-detached dwelling for City Parkland Dedication

Demolition

66 Soudan Ave

188 m away · 66 Soudan Ave · Toronto-St. Paul's

Approved 22 Jan 2025

Demolish the existing two storey semi-detached dwelling for City Parkland Dedication

Demolition

64 Soudan Ave

191 m away · 64 Soudan Ave · Toronto-St. Paul's

Approved 22 Jan 2025

Demolish the existing two storey semi-detached dwelling for City Parkland Dedication

Show 21 moreShow fewer
Demolition

62 Soudan Ave

194 m away · 62 Soudan Ave · Toronto-St. Paul's

Approved 22 Jan 2025

Demolish the existing two storey semi-detached dwelling for City Parkland Dedication

Demolition

60 Soudan Ave

197 m away · 60 Soudan Ave · Toronto-St. Paul's

Approved 22 Jan 2025

Demolish the existing two storey dwelling for City Parkland Dedication

Demolition

61 Brownlow Ave

423 m away · 61 Brownlow Ave · Toronto-St. Paul's

Approved 24 Sep 2025

Demolishing the townhouse for the construction of a residential apartment building.(61-75 Brownlow Avenue)

Demolition

21 Imperial St

583 m away · 21 Imperial St · Toronto-St. Paul's

Approved 23 Oct 2026

Proposal to demolish the existing 2 storey office building located at 21 IMPERIAL ST only.

Demolition

25 Imperial St

592 m away · 25 Imperial St · Toronto-St. Paul's

Approved 23 Oct 2026

Proposed demolition of the existing 5-storey commercial building.

Demolition

88 Colin Ave

650 m away · 88 Colin Ave · Toronto-St. Paul's

Approved 2 Jun 2026

Rl Urban Innovations Inc

Proposal to demolish existing single family dwelling.

Demolition

17 Henning Ave

678 m away · 17 Henning Ave · Eglinton-Lawrence

Approved 10 Apr 2025

Demolition of existing 2 storey brick dwelling. Proposed a 34-story Residential building with two underground parking levels. SPA Application No. 23 179321 NNY 08 SA

Demolition

19 Henning Ave

683 m away · 19 Henning Ave · Eglinton-Lawrence

Approved 10 Apr 2025

Demolition of existing 2 storey brick dwelling. Proposed a 34-story Residential building with two underground parking levels. SPA Application No. 23 179321 NNY 08 SA

Demolition

21 Henning Ave

688 m away · 21 Henning Ave · Eglinton-Lawrence

Approved 26 May 2025

Demolition of existing 2 storey brick dwelling. Proposed a 34-story Residential building with two underground parking levels. SPA Application No. 23 179321 NNY 08 SA

Demolition

23 Henning Ave

688 m away · 23 Henning Ave · Eglinton-Lawrence

Approved 26 May 2025

Demolition of existing 2 storey brick dwelling. Proposed a 34-story Residential building with two underground parking levels. SPA Application No. 23 179321 NNY 08 SA

Demolition

25 Henning Ave

692 m away · 25 Henning Ave · Eglinton-Lawrence

Approved 26 May 2025

Demolition of existing 2 storey brick dwelling. Proposed a 34-story Residential building with two underground parking levels. SPA Application No. 23 179321 NNY 08 SA

Demolition

27 Henning Ave

697 m away · 27 Henning Ave · Eglinton-Lawrence

Approved 26 May 2025

Demolition of existing 2 storey brick dwelling. Proposed a 34-story Residential building with two underground parking levels. SPA Application No. 23 179321 NNY 08 SA

Demolition

29 Henning Ave

699 m away · 29 Henning Ave · Eglinton-Lawrence

Approved 25 Aug 2025

Demolish the existing two storey semi-detached dwelling to accomodate a future redevelopment.

Demolition

31 Henning Ave

704 m away · 31 Henning Ave · Eglinton-Lawrence

Approved 25 Aug 2025

Demolish the existing two storey semi-detached dwelling to accomodate a future redevelopment.

Demolition

140 Merton St

736 m away · 140 Merton St · Toronto-St. Paul's

Approved 16 Mar 2026

The proposed development involves the demolition of the existing building and parking lot, and the construction of a 28-storey mixed use building with underground parking, outdoor amenity spaces, pedestrian walkways, a…

Demolition

295 Balliol St

760 m away · 295 Balliol St · Toronto-St. Paul's

Approved 7 Mar 2025

Demolish an existing 2-storey semi-detached building on the lands municipally known as 293-295 Balliol Street. The lands will be later improved with the construction of a residential apartment building as noted in the…

Demolition

180 Merton St

761 m away · 180 Merton St · Toronto-St. Paul's

Approved 4 Jun 2026

Proposed demolition of row of townhouses/buildings to accommodate proposed project for 45-storey mixed-use residential building - Re: 170/180 Merton St

Demolition

39 Montgomery Ave

776 m away · 39 Montgomery Ave · Eglinton-Lawrence

Approved 4 Mar 2026

Proposal to demolish existing SFD with no replacement building for future Park Development

Demolition

55 Montgomery Ave

795 m away · 55 Montgomery Ave · Eglinton-Lawrence

Approved 10 Apr 2025

Proposal to demolish the existing 2 storey SFD-detached dwelling.

Demolition

34 Montgomery Ave

796 m away · 34 Montgomery Ave · Eglinton-Lawrence

Approved 6 May 2025

First Capital (king Liberty-barrymore) Corporation

Proposal to demolish the two-storey residential building.

Loud nights

Hours the city has already allowed.

Continuous Concrete Pour

8 Brownlow Avenue (northwest Of Brownlow And Souda

326 m away · 8 Brownlow Ave · Toronto-St. Paul's

Allowed 1 May 2026 – 30 Oct 2026

Hours 7:00 a.m.–12:30 a.m.

Soudan-brownlow Properties

Construction

Canada Square Office Retrofit

369 m away · 2180 Yonge St · Toronto-St. Paul's

Allowed 10 Jul 2026 – 31 Oct 2026

Hours 7:00 p.m.–11:00 p.m.

Setup 8 Jun 2026 – 27 Jun 2026, 7:00 p.m.–11:00 p.m.

Tear down 24 Mar 2027 – 5 Apr 2027, 7:00 p.m.–11:00 p.m.

Ellisdon Corporation

Construction

Canada Square Office Retrofit

369 m away · 2180 Yonge St · Toronto-St. Paul's

Allowed 1 Nov 2026 – 30 Jun 2027

Hours from 7:00 p.m.

Ellisdon Corporation

Show 8 moreShow fewer
Continuous Concrete Pour

The One Seventy

588 m away · 170 Roehampton Ave · Toronto-St. Paul's

Allowed 7 Aug 2026 – 7 Feb 2027

Hours from 7:00 p.m.

Clark Construction Management Inc.

Continuous Concrete Pour

140 Merton Street Development

736 m away · 140 Merton St · Toronto-St. Paul's

Allowed 17 Nov 2026 – 17 May 2027

Hours 7:00 a.m.–11:59 p.m.

Ellisdon Residential Inc.

Construction

Yonge And Roselawn Project

814 m away · 2400 Yonge St · Eglinton-Lawrence

Allowed 1 Jan 2026 – 31 Dec 2026

Hours 6:00 a.m.–10:00 p.m.

Skygrid Construction Inc

Continuous Concrete Pour

30 Merton

815 m away · 30 Merton St · Toronto-St. Paul's

Allowed 2 Jul 2026 – 31 Dec 2026

Hours 7:00 a.m.–11:59 p.m.

Skygrid Construction Inc.

Continuous Concrete Pour

241 Redpath

833 m away · 241 Redpath Ave · Don Valley West

Allowed 9 Sep 2026 – 31 Mar 2027

Hours from 7:00 p.m.

Bluescape 241 Redpath Inc.

Continuous Concrete Pour

241 Redpath

833 m away · 241 Redpath Ave · Don Valley West

Allowed 16 Oct 2026 – 26 Oct 2026

Hours 7:00 a.m.–10:00 p.m., 7:00 a.m.–9:00 p.m.

Bluescape 241 Redpath Inc.

Continuous Concrete Pour

241 Redpath Ave

833 m away · 241 Redpath Ave · Don Valley West

Allowed 2 Nov 2026 – 18 Nov 2026

Hours 7:00 a.m.–10:00 p.m.

Bluescape 241 Redpath Inc.

Events

On the city's calendar. Check before you go.

Environmental

Seed-to-Habitat Workshop: Hands-on Seed Processing Workshop

905 m away · 200 Eglinton Ave W · Eglinton-Lawrence

On 21 Nov 2026

Free

Designed for participants from the Part 1 webinar, this follow-up free workshop will provide hands-on experience for cle

Add to calendar

Plans you can answer

Someone has asked the city for a change. Nothing here is a decision.

Site plan

158 Soudan Ave

207 m away · 158 Soudan Ave · Toronto-St. Paul's

Asked 26 Mar 2025

Under Review

Site Plan Control for a 56-storey residential tower that will have a total of 46,547 square metres of residential gross floor area ("GFA") and a total of 674 total dwelling units (including the 13 required rental replacement units). See Related Rezoning file (25 135273 STE 12 OZ) Jan 2026 Revised Submission - Zoning…

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Patrick Miller · [email protected].

Site plan

18 Brownlow Ave

335 m away · 18 Brownlow Ave · Toronto-St. Paul's

Asked 23 Jul 2025

NOAC Issued

Site Plan Amendment to alter the development standards for the 21-storey residential building (previously approved under 23 152381 STE 12 SA), by increasing the height and number of storeys (from 21-storeys to 26-storeys), increasing the permitted gross floor area and permitted projections, revising minimum setbacks…

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Shane Taylor · [email protected].

Rezoning

216 Soudan Ave

347 m away · 216 Soudan Ave · Toronto-St. Paul's

Asked 13 Nov 2024

Under Review

Zoning By-law Amendment for a 45-storey purpose built rental residential building containing 527 new dwelling units, and a total of 32,900.29 sq. m of residential gross floor area (GFA).

How to respond

You can send a written comment to the city planner, and you can ask to speak when this ward's community council hears the rezoning. That council recommends. City Council makes the decision.

Next sitting on the published 2026 schedule: Toronto and East York Community Council, 25 Nov 2026, 9:30 a.m., Committee Room 1, Toronto City Hall.

Write Patrick Miller · [email protected].

Show 21 moreShow fewer
Site plan

2045 Yonge St

353 m away · 2045 Yonge St · Toronto-St. Paul's

Asked 22 Aug 2022

Under Review

Proposed redevelopment of the site for an 11-storey mixed-use building fronting onto Yonge Street, and connected to seven 3-storey townhouse units fronting onto Tullis Drive.

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Cameron Williamson · [email protected].

Condominium plan

2128 Yonge St

355 m away · 2128 Yonge St · Toronto-St. Paul's

Asked 28 Oct 2021

Under Review

*** Draft Plan of Condominium for 80 units.

How to respond

This is a condominium plan, usually tied to a rezoning. A written comment goes to the city planner. Height and use are argued on the rezoning, when there is one.

Write Kai Zhou · [email protected].

Rezoning

2180 Yonge St

369 m away · 2180 Yonge St · Toronto-St. Paul's

Asked 21 Dec 2020

Under Review

INACTIVE Zoning By-law Amendment application to permit phased development of five mixed-use buildings at 45, 55, 60 and 65 storeys with 2,892 residential units. Proposal includes a new public plaza, open spaces, street connections, a community use facility, and public park. Related OPA application: 22 242145 STE 12 OZ

How to respond

You can send a written comment to the city planner, and you can ask to speak when this ward's community council hears the rezoning. That council recommends. City Council makes the decision.

Next sitting on the published 2026 schedule: Toronto and East York Community Council, 25 Nov 2026, 9:30 a.m., Committee Room 1, Toronto City Hall.

Write Patrick Miller · [email protected].

Rezoning

2180 Yonge St

369 m away · 2180 Yonge St · Toronto-St. Paul's

Asked 23 Dec 2022

Under Review

Official Plan application to permit phased development of five mixed-use buildings at 45, 55, 60 and 65 storeys with 2,892 residential units. Official Plan Amendment requested to amend policies and Map 21-9 within the Yonge-Eglinton Secondary Plan. Related ZBA application: 20 232714 STE 12 OZ

How to respond

You can send a written comment to the city planner, and you can ask to speak when this ward's community council hears the rezoning. That council recommends. City Council makes the decision.

Next sitting on the published 2026 schedule: Toronto and East York Community Council, 25 Nov 2026, 9:30 a.m., Committee Room 1, Toronto City Hall.

Write Patrick Miller · [email protected].

Site plan

55 Eglinton Ave E

374 m away · 55 Eglinton Ave E · Toronto-St. Paul's

Asked 27 Apr 2018

Under Review

INACTIVE Site Plan applciation for a total of 40,886.39 square metres of gross floor area (GFA) over 50 storeys. This GFA includes 253.58 square metres of at-grade retail fronting Eglinton Avenue East, and 6,409.82 square metres of office space to be located on Floors 2-6. A total of 461 residential units are proposed…

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Patrick Miller · [email protected].

Rezoning

29 Berwick Ave

397 m away · 29 Berwick Ave · Toronto-St. Paul's

Asked 10 Jul 2025

OMB Appeal

The application proposes to redevelop the subject site by constructing a 49-storey residential building with a height of 162.15 m + 8.0 m MPH. The proposed redevelopment consists of a total gross floor area (GFA) of 34,588.9 sq. m., which results in a total Floor Space Index (FSI) of 19.07 times the area of the lot.…

How to respond

This file is at the Ontario Land Tribunal. The next community council sitting is not the hearing.

Write Patrick Miller · [email protected].

Subdivision

2050 Yonge St

420 m away · 2050 Yonge St · Toronto-St. Paul's

Asked 8 Nov 2021

Under Review

2 blocks

How to respond

You can send a written comment, and you can ask to speak at community council. City Council decides a plan of subdivision.

Next sitting on the published 2026 schedule: Toronto and East York Community Council, 25 Nov 2026, 9:30 a.m., Committee Room 1, Toronto City Hall.

Write Kai Zhou · [email protected].

Site plan

2050 Yonge St

420 m away · 2050 Yonge St · Toronto-St. Paul's

Asked 8 Nov 2021

Under Review

Site Plan Approval for a 14-storey mixed-use building having a non-residential gross floor area of 2863 square metres, and a residential gross floor area of 15683 square metres. 164 residential units are proposed.

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Kai Zhou · [email protected].

Rezoning

120 Eglinton Ave E

422 m away · 120 Eglinton Ave E · Toronto-St. Paul's

Asked 30 Apr 2025

OMB Appeal

The redevelopment proposes a 70-storey mixed-use building with 187.4 sq. m. of retail space at-grade and 555 residential dwelling units above, resulting in a total gross floor area (GFA) of 39,275.7 sq. m., a total Floor Space Index (FSI) of 26.06, pursuant to GFA calculations under By-law 569-2013.

How to respond

This file is at the Ontario Land Tribunal. The next community council sitting is not the hearing.

Write Shane Taylor · [email protected].

Site plan

61 Brownlow Ave

423 m away · 61 Brownlow Ave · Toronto-St. Paul's

Asked 25 Aug 2021

NOAC Issued

Site Plan application to permit a residential building with two towers, 59 and 55 storeys , comprising 1,374 residential units, daycare facility and a gross floor area of 97,194 square metres. The proposal involves rental replacement.

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Shane Taylor · [email protected].

Condominium plan

61 Brownlow Ave

423 m away · 61 Brownlow Ave · Toronto-St. Paul's

Asked 10 Sep 2021

Under Review

*** Draft Plan of Standard Condominium to permit 384 residential units in a 35-storey residential building with a 2-level underground parking garage containing 69 vehicular parking spaces.

How to respond

This is a condominium plan, usually tied to a rezoning. A written comment goes to the city planner. Height and use are argued on the rezoning, when there is one.

Write Cameron Williamson · [email protected].

Site plan

45 Berwick Ave

430 m away · 45 Berwick Ave · Toronto-St. Paul's

Asked 10 Jul 2025

Under Review

The application proposes to redevelop the subject site by constructing a 49-storey residential building with a height of 158.2 m + MPH. The proposed redevelopment consists of a total gross floor area (GFA) of 34,641.7 sq. m., which results in a total Floor Space Index (FSI) of 19.1 times the area of the lot. The…

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Patrick Miller · [email protected].

Site plan

1 Eglinton Ave E

433 m away · 1 Eglinton Ave E · Toronto-St. Paul's

Asked 15 Oct 2021

Under Review

Site Plan Approval for a 65-storey mixed-use building having a non-residential gross floor area of 11,225.70 square metres, and a residential gross floor area of 43,684.60 square metres. A total of 600 residential dwelling units are proposed.

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Patrick Miller · [email protected].

Condominium plan

1 Eglinton Ave E

433 m away · 1 Eglinton Ave E · Toronto-St. Paul's

Asked 15 Oct 2021

Under Review

*** Draft Plan of Condominium for 600 residential dwelling units.

How to respond

This is a condominium plan, usually tied to a rezoning. A written comment goes to the city planner. Height and use are argued on the rezoning, when there is one.

Write Patrick Miller · [email protected].

Subdivision

150 Eglinton Ave E

434 m away · 150 Eglinton Ave E · Toronto-St. Paul's

Asked 16 Sep 2021

Under Review

Draft Plan of Subdivision for the creation of 5 lots.

How to respond

You can send a written comment, and you can ask to speak at community council. City Council decides a plan of subdivision.

Next sitting on the published 2026 schedule: Toronto and East York Community Council, 25 Nov 2026, 9:30 a.m., Committee Room 1, Toronto City Hall.

Write Shane Taylor · [email protected].

Subdivision

90 Eglinton Ave E

438 m away · 90 Eglinton Ave E · Toronto-St. Paul's

Asked 16 Sep 2021

Under Review

Draft Plan of Subdivision to create 3 blocks.

How to respond

You can send a written comment, and you can ask to speak at community council. City Council decides a plan of subdivision.

Next sitting on the published 2026 schedule: Toronto and East York Community Council, 25 Nov 2026, 9:30 a.m., Committee Room 1, Toronto City Hall.

Write Shane Taylor · [email protected].

Site plan

110 Eglinton Ave E

441 m away · 110 Eglinton Ave E · Toronto-St. Paul's

Asked 15 Aug 2022

Under Review

The proposed development consists of a 9-storey podium topped with two residential towers that are 57 and 59 storeys in height and a 3-level underground garage. The total GFA is approximately 95,000 square metres, comprising of approximately 77,000 square metres of residential GFA, and approximately 18,000 square…

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Shane Taylor · [email protected].

Site plan

181 Eglinton Ave E

441 m away · 181 Eglinton Ave E · Toronto-St. Paul's

Asked 14 Jul 2022

Under Review

Site Plan Application for proposed 21-storey buidling and three-levels of underground parking, excluding mechanical penthouse. The proposal includes 11,242.7 square metres of residential and 237.4 square metres of retail use. The building includes 139 unit and 23 vehicular parking spaces.

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Shane Taylor · [email protected].

Site plan

160 Eglinton Ave E

448 m away · 160 Eglinton Ave E · Toronto-St. Paul's

Asked 11 Apr 2022

Under Review

Site Plan application to permit a 61-storey multi-tower mixed use building with a maximum gross floor area of 90,000 square metres, 201 parking spaces, 1,329 bicycle parking spaces, and a north-south midblock connection.

How to respond

Site plan approval is usually a staff decision. A written comment to the city planner is the step on this file. It is not a community-council deputation.

Write Shane Taylor · [email protected].

Rezoning

732 Mount Pleasant Rd

450 m away · 732 Mount Pleasant Rd · Toronto-St. Paul's

Asked 17 Apr 2026

Under Review

Zoning By-law Amendment application to allow for the development of a 36-storey mixed-use building comprised of a 4-storey podium and a 32-storey tower element. The proposed building includes approximately 65 square metres of non-reisdential space at grade and 396 residential dwelling units.

How to respond

You can send a written comment to the city planner, and you can ask to speak when this ward's community council hears the rezoning. That council recommends. City Council makes the decision.

Next sitting on the published 2026 schedule: Toronto and East York Community Council, 25 Nov 2026, 9:30 a.m., Committee Room 1, Toronto City Hall.

Write Patrick Miller · [email protected].